Bergh Apton Progress Update

Bergh Apton
Bergh Apton
Bergh Apton
Bergh Apton
Bergh Apton
Bergh Apton

Progress on the new residential development at Cookes Road, Bergh Upton is going well.

Window and door installation has been carried out on 'Plot 6' including roof coverings in preparation for underfloor heating installation and ground floor screed.

​The masonry work is being raised above floor joists on 'Plot 10'.

Internal works are being carried out on 'Plot 4', the screen has been laid in preparation for 1st fix M&E, Internal partitions have been erected and staircases installed.

The detention basin has been completed along with the commencement of the conveyance swale.