12.06.17Lowestoft works progressing well
12.06.17
The project of 16 purpose built residential units at Church Green in Lowestoft is progressing well.
The roof construction has been completed on plots 5-16 with the roof coverings to commence this week. M&E & carpentry first fix has also commenced in these plots.
The masonry has commenced to plots 1-4 to wall plate level Wardens House. The concrete ground floor slab will commence shortly which will allow the superstructure masonry works to commence.