Diss Corn Hall Progress Update

Pentaco Construction are pleased to say that progress at the Diss Corn Hall site is going well and have the following update from our Contracts Manager.

“The demolition of the existing extensions has now been completed and reduced level dig / underpinning has commenced for the new extension.”

“Breaking up of the existing Corn Hall floor has been completed and reduced level excavation is in progress ahead of the new slab construction.”